Nov
18
to Dec 7
Sep
14
to Sep 15
Jun
11
Tower Crane Erection
The South Tower crane will be erected along N Moore Street near 19th Street. The crane used for the erection shall be stationed inside of the excavation.
Jun
3
to Jun 4
Reestablish Site Fence along N Lynn Street
On June 3rd and 4th, the site fence will be reestablished during the standard Arlington County road closure hours along N Lynn Street.
Sep
25
to Sep 26
Jul
28
Demolition Complete
Demolition of the RCA Building will be complete by the end of July 2023.
Mar
27
Begin RCA Building Demolition - North Garage
The first phase of demolition will begin at the north garage area. We anticipate this will take about two weeks to complete. Once the north garage is demolished, we will begin knocking down the pedestrian sky bridge over N. Moore St. All demolition associated with the bridge will only take place on weekends due to the closure of N. Moore St.