UPCOMING WORK

CBG Building Company continues to go vertical with the new structure and expects to top out in the summer of 2025. Follow-on work, including exterior framing and facade, will commence in early 2025.

Wet and dry utilities are substantially complete, while traffic signalization relocation work is ongoing.

Hover or click on a calendar item for details regarding any work activities that will have specific or atypical community impacts (i.e. road closures, night work, etc.). If no items are indicated, no specific community impacts are anticipated at this time.


LATEST PROGRESS

February 2025

The building structure continues to go vertical as the first six floors have been constructed.